How to change a Purchase Requisition after it has been created?
Use Transaction ME52N. Check to see if the PR has already had a PO issued against it. If so, you must inform the Purchasing Group. Check if the PR has been approved. If so, you may only make changes to a limited extent and may be subject of approval. Check if the PR was created by MRP. In this case, you don’t have much control over the modification process.
All changes to items are logged and stored. Information stored includes when the information was changed, who changed it, what the changes were, etc. Select the desired item in the item overview and choose Go To –> Statistics –> Changes.
If you like this post, you may as well like these too:
- Purchase Requisition… How to? Quick How to tips on Purchase Requisition Creating A Purchase Requisition Use Transaction ME51N Searching for “des vendor” in Item Overview portion of screen Finding Vendor Address Ordering for...
- Processing Non-Assigned Purchase Requisitions Once the Purchase Requisitions are generated, additional standard functions are provided by the SAP System for converting these requisitions into respective purchasing documents (purchase orders, contract release orders, scheduling...
- Processing Assigned Purchase Requisitions The following functions are available in SAP R/3 for the optimized conversion of requisitions into purchase orders: Purchase requisition items with source of supply If a source has already...
- Document Changes and Change Control Document Changes and Change Control Document change rules can be either user defined or predefined in the system. Only Certain feilds are modifiable once the document changes are posted....
- Blanket Purchase Order With certain procurement transactions, the costs of procurement are disproportionately high in relation to the value of the material or service involved. This is frequently the case of office...
















Leave a Reply