How to Create Source List?

Print This Post Email This Post Written by rajivsharma.sap on Nov 26th, 2008 | Filed under: Material Management (MM)

Use Transaction ME01. Enter the Material Number and the Plant Data. Enter source list records, validity period, period of time material is procurable, Vendor Number, responsible Purchasing  Organization (or number of the Agreement or Contract), PPL (if the material can be procured from another plant), Fixed Source (?), MRP control.

Also, a check should be done to see whether any source list records overlap. To do so, choose Source List –> Check.

If you like this post, you may as well like these too:

  1. Source List The purpose of the source determination process is to automatically assign a source of supply to a purchase requisition. If the requester has set the Source Determination indicator in the...
  2. What is the Source List? The Source List identifies preferred sources of supply for certain materials. If the Source List has been properly maintained, it will identify both the source of a material and the...
  3. Source Code: Few simple examples 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29...
  4. Source Code: Designing a report REPORT ZSOURCE0104. * Declaration of a work area for a Dictionary tableTABLES CUSTOMERS. * Internal table used as snapshot of the database tableDATA ALL_CUSTOMERS LIKE CUSTOMERS OCCURS 100 WITH HEADER...



This website uses IntenseDebate comments, but they are not currently loaded because either your browser doesn't support JavaScript, or they didn't load fast enough.

Leave a Reply

  • Subscribe to RSS

  • Free Ebooks